Table
of Contents
1.
Scope
/Objectives
2.
Reference
3.
Access/Egress
4.
Logistics
5.
Health
and Safety Hazards
6.
Definitions
7.
Responsibilities
/ Supervision
8.
Procedures
/Method to be Employed
9.
Training
10.
Working
hours
11.
House
keeping
12.
Manpower
Requirement & Supervision
13.
Material
Requirement
14.
Plant
& Equipment Requirement
15.
Q.C
Approvals and other Documentation
16.
Supporting
documentation
17.
Distribution
18.
Other
information
19.
Site
Safety Engineer’s Approval
20.
Attachments
(Compulsary)
·
Risk
Assessment
·
Quality
Control Inspection Checklist
·
Inspection
and Test Plan
·
PERI
– LICO ( Lightweight Column Formworks)
·
Main
Villa Elevator Shaft Frameworks
·
Main
Villa Column Construction
·
Pool
Annex Column Construction
·
Guard
House Column construction
1. SCOPE
& OBJECTIVES
The Purpose of this procedure is to ensure that Concreting works of Column and
Shaft are executed in accordance with the contract requirements,
hazards are analysed, safety procedures implemented all quality
assurance/control activities are conducted in a systematic manner, works
inspected and conformance is verified and documented for Beach Villa on BVN 55
to 60 at The Pearl Qatar.
2. REFERENCES
Contract Drawing and
specification
2.1
QCS Section 05 “Concrete Supply – Construction – Testing”
2.2
Project Health, Safety and Environmental Guidelines
2.3
Project “inspection and Test Plan –
Civil Works”
2.4
British Standard : BS 8110 – Structural use of concrete
2.5
British Standard : BS 1881 – Testing of concrete
2.6
American Standard : ACI 305 r – Hot Weather Concreting
2.7
“Method Statement for Concreting of Raft for Main Villa.”
2.8
Project Specification Section 5.
3. ACCESS/
EGRESS
Adequate access and egress
should be provided to the site. All the personnel should wear basic personnel
protective equipment. All the equipment, tools and tackles being used for the
work should be in good working condition and maintained. All the personnel will
be provided with toolbox talk on the procedures to execute the work safely.
Access will be through designated
entrance and exit pathways.
4. LOGISTICS
Contractor will deploy a
dedicated team for the concreting works.
5. HEALTH
& SAFETY HAZARDS
Safety of the personnel and
properties is to be given prime importance and all the works to be carried out
without causing any accidents or property damages. Concrete works involves the
following activities: shuttering and de-shuttering, fabricating and fixing
reinforcements steel, transportation of concrete and placing concrete at site.
5.1
All workers involved will be trained in hazards
recognition and control measures necessary especially in safe manual handling
techniques and the need to keep all access clear to work area always.
5.2
Safety system / method of work covering concrete
receiving, placing on site, pouring operations will be established by member
management team.
5.3
Appropriate personal protective equipment (PPE) should
be worn at all times.
5.4
Secure barricades within the area whenever necessary.
5.5
Washing facilities should be provided.
5.6
Formwork should be checked before concrete is put in
place.
5.7
The accumulation of concrete spillage should be
prevented.
5.8
The effect of weather conditions should be considered
and appropriate allowances made especially on hot weather.
5.9
Only qualified and trained personnel will do the task.
6. DEFINITIONS
AEB – Arab Engineering Bureau
(Consultant/Engineer)
AMTC – Abdullah Al Muftah Trading
and Contracting Co., w.l.l (Main Contractor)
MS – Method Statement
QCP – Quality Control Procedures
ITP – Inspection and Test Plan
ITA – Independent Testing Agency
7. RESPONSIBILITIES
/ SUPERVISION
7.1
Project
Engineer shall be responsible for the execution of this procedure and to
ensure that works are undertaken in a
safe manner to the requisite quality and to the time agreed timescale. He shall
advise and coordinate with other
contractors pertaining to access and interface requirements related to the
excavation works to be undertaken.
7.2
Site Engineer shall be responsible
for the site implementation of this procedure including control and the safety of the workers.
7.3
Surveyor in coordination with site
engineer has the responsibility to perform all survey works according to the IFC drawings.
7.4
QA/QC Inspector shall be responsible
for the supervision of tests and inspection, control approvals for testing and
inspection plan and to arrange documentation required.
7.5 Safety
Officer shall
be responsible for the strict implementation of safety procedure during work
commencements.
8. PROCEDURE / METHOD TO BE EMPLOYED:
8.1 General
a. Testing and frequency of
material related to concrete, design mixes, batching and mixing of concrete, transporting of concrete, tests on
green and hardened concrete and submittals shall be made in accordance with Contract Technical Specification
and the latest edition of Qatar Construction Specification (QCS).
b. Delivery, Storage, Testing
frequency of reinforcement bars and submittals shall be made in accordance with
BS 4449.
8.2 Reinforcement
a. All steel reinforcement
shall comply with Part 11.2 Section 5 of QCS.
b. Reinforcement bars shall be
stored over timber beams, at least 20 cm above ground level. All the bars shall
be protected from weather,
dust and humidity by covering with tarpaulins or polyethylene sheets.
c. Bar bending schedules in
accordance with BS 8110 shop drawings shall be prepared by approved steel reinforcement Fabrication Company (by ERF).
d. Cutting, Bending and fixing
of reinforcement shall be carried in compliance to BS 8666 and Part 11.4 and 11.5 Section 5 of Qatar Construction
Specification (QCS) and as per the approved bar bending schedules and shop drawings.
e. Lap
lengths of reinforcement shall be according or indicated in the approved IFC
drawing.
f. Minimum concrete cover of
75 mm for exterior face and 40 mm for the interior face of wall shall be maintained as per the approved
drawings and specifications.
g. The concrete spacers blocks
dimension shall be as per specified thickness cover and shall be made with the same mix proportion as the structures.
h. All necessary spacers and
U-bars shall be provided to maintain the specified covers. U-bars bars shall be
provided at 1 meter intervals on both
directions to maintain the minimum concrete cover or should meet the approved drawings &
specification requirements.
i. The fabricated bars shall
be kept in position as approved in shop drawings and tied with approved tie
wires. The ends or wire shall
be bent into the concrete.
8.3 Formworks
a. All formworks shall be done
in accordance to BS 5975 and BS 8110; Section 5 of Qatar Construction Specification (QCS).
b. Scaffolding for working and
access platform shall be erected and inspected by trained personnel.
c. Formworks shall be design
and supply by PERI Qatar (see attached – Lightweight column formwork ) and
shall be in accordance with BS 5975 and BS8110; Part 9, Section 5 of Qatar
construction Specification (QCS). See also attached Main Villa Elevator Shaft
Framework.
d. Formworks to be used shall
be marine plywood furnish in largest practicable sizes to minimize number of joints.
e. Fabricate and install forms
for easy removal to avoid damage to cast concrete surfaces when stripping. The formworks shall be braced enough to
withstand external forces during concrete casting.
f. Form ties shall be
factory-fabricated for securing formworks and shall be installed as per PERI
Qatar design and
recommendation. Form ties designed to resist lateral pressure during concrete
placing.
g. Necessary construction joints
shall be provided, with a provision of approved high strength PVC water stop
centrally
located in the wall thickness, if applicable.
h. Lines, levels and dimensions shall be mark by Surveyor before and after
formworks installation and shall be maintain
during concrete casting.
i. Temporary opening shall be
provided for cleanouts and shall be closed and securely braced to prevent loss of concrete mortar.
j. Coat contact surfaces of
forms with form-release agent before securing the formworks in the final
position.
k. The periods of striking /
removal of formwork shall be 1 day or in compliance with Table 9.1 of QCS
Section 5 Part 9.5.2
8.4 Installation of Pipes and
wall opening for MEP services
a. All the Embedded Services /
sleeves and opening for MEP works shall be in compliance with approved MEP Drawings.
b. Place and secure embedded items
and services tied enough not to displace during concrete casting.
c.
Additional
reinforcement trimmer bars shall be installed around the wall opening and pipe
sleeves as per the indicated details
for trimming bars on hole in solid wall / slab in the structural drawings.
d. All MEP services embedment shall
be installed to correct sizes, line, and level to be inspected and approved by AEB representative prior to
closing of formwork.
8.5 Transportation
of concrete
a. Transportation, delivery
and handling of ready mix concrete shall be in accordance with the requirements
of BS 8500 and BS EN 206-1
and Part 8, Section 5 of Qatar Construction Specification (QCS).
b. Concrete shall be conveyed
from the mixer to its place in the works as rapidly as possible.
c. Monitoring of time between
placing of concrete shall be strictly observed and is short as possible enough
to prevent formation of cold joints.
8.6 Concreting
a. Structural concrete shall be as per approved mix design specified on
structural drawings and in compliance with Part 8 Section 5 of Qatar
Construction Specification (QCS).
b. Structural concrete works shall commence upon completion / approval of
reinforcement and formwork activities.
c.
Site Engineer shall ensure that the formwork
provided for the required shape and dimensions are in accordance with the
drawings.
d. Reference levels for top of the concrete (see attached Main
Villa Column Construction, Pool Annex Column Construction and Guard House
Column Construction) shall be provided by Surveyor at the liner of
forms. Steel pins / nails shall be provided at intermediate areas as guide
levels for the required elevation.
e. Adequate working platforms shall be provided for compaction / vibration
and other activities.
f.
All the surfaces shall be cleaned. Foreign
matters such as saw dust, wooden and wire pieces shall be removed prior to
Concreting.
g. Site Engineer shall ensure the availability of standby vibrators;
pokers, hand tools, hessian clothes, polythene sheets and enough water shall be
available on site.
h. The number and size of vibrators shall be such as to ensure thorough
compaction of the entire volume of concrete poured. Standby units shall also be
provided.
i.
Concrete placement sequence shall be planned
in a manner so that to have minimum repositioning of the transit mixer
/concrete pump/crane if any.
j.
All the chutes, buckets, pokers and hand
tools shall be cleaned with water before and after concreting.
k.
Surfaces of the formworks shall be kept moist
and reinforcement shall be sprayed with a small amount of water prior to
starting of pour.
l.
Concrete shall be ordered only after approval
of the IR to place concrete by AEB representative.
m. During hot weather conditions the following precautions / preventive
measures shall be taken as applicable / required to control the effect of high
ambient temperature, and low relative humidity :
·
Cooled water / ice shall be used for batching / mixing concrete. Water
shall be cooled by using chillers, ice (if necessary) to maintain concrete
temperature equal to or below 32 deg. C.
·
Maximum shade temperature during placing of concrete shall be not more
than 35 deg. C.
·
To keep cool, transit mixer drum surface shall be painted white, which
shall minimize solar heat gain.
·
Transit mixers drum surfaces shall be kept cool by covering them with
wet Hessian clothes, damp by spraying water. Water shall be sprayed to the
concrete mixer drum before batching and during delivery.
·
Pouring shall be planned / scheduled on the evening hours when the
weather condition is favourable and adverse exposure of the concrete to the
environment can be avoided.
·
Time to transport, place, consolidate and finish the concrete shall be
minimized by proper planning and coordination.
n. Concrete shall be delivered to site and used within 90 minutes after the
introduction of water and shall be placed and compacted to its final position.
o. The delivery ends of the pump hose shall be kept as close as possible to
the delivery points; the drop height shall be minimized to 1.5m (max) to avoid segregation.
p. To maintain the drop height, a flexible hose shall be connected to the
outlet of the pump then it will insert inside the wall forms or by specially
designed drop holes around 200x200 mm shall be provided in the shuttering at
every 2 meter C/C and at every 1.5 meter height of shuttering to keep the
minimum drop height.
q. Vibrators shall be operated at regular intervals to produce dense,
compact, homogeneous concrete surface without segregation and ensure thorough
compaction of the entire volume of the concrete.
r.
Vibrators shall be withdrawn slowly to
prevent the formation of voids and shall not be placed against compacted
concrete. It shall not be used for transporting concrete inside forms.
s.
The concrete will be vibrated as work
proceeds. Once the concrete has reached the required height, the exposed
surface will be trowel and covered for protection.
8.6 Curing of Concrete
a. Water to be used for curing shall be free from salt, harmful matters and
other impurities.
b. Concrete shall be cured to a minimum of seven days.
8.7 Dimension Tolerance for
Concreting works (As per QCS Part 9.7; Section 5)
a. All laying-out dimensions ±
5mm
b. Section of concrete members ±
5mm
c.
Surface of foundations against ground ±
10mm
d. Top surfaces of foundations, bases and piers ±
20mm
e. Surface level of floor slabs (5-meter straightedge) ±
5mm
f.
Surface level of slab to datum ±
10mm
g. Plumb of columns and wall in storey height ±
5mm
h. Plumb of column and wall in full building height ± 20mm
i.
Inside faces of elevator shafts in storey
height ±
5mm
j.
Inside faces of elevator shafts in full
building height ±
10mm
8.8
Testing:
a. Testing on concrete aggregates
is to be as per QCS Section 05 part 6.4.
b. Slump and temperature of fresh
concrete supplied to site shall be monitored and checked in accordance with QCS
Section 05.
c.
Strength
testing (cubes): 3 cubes for every 25 cum minimum or 1 set per day that
concrete is placed, one tested at 7 days and two tested at 28 days.
d. Testing of steel reinforcement
will be done every delivery to have random checking in conformity with QCS
section 5 part 11.
8.9
Protection of Sub Structures:
All
structures below ground to be protected with an approved water proofing system.
8.10 Embedment’s:
a. Anchor bolts to be fixed to
correct level and line with templates and secured firmly to prevent any
displacements during concreting.
b. Corner Angles to be embedded in
concrete shall be placed in position and suitably fixed to form and or tied to
rebars.
c.
PVC
Ducts and Sleeves are placed in position, and supported adequately prior to
concreting, by securing to formwork and or rebars.
d. No welding shall be done to the
rebars, for fixing the embedments.
9
TRAINING
Relevant
trainings and orientations have been provided to person who will perform their
specified task.
10 WORKING
HOURS
As
per approved site schedule.
11 HOUSE
KEEPING
Working Areas will be kept
clean by disposing the waste materials at the designated areas. At the end of
days’ work, installation supervisor will ensure that the debris are
disposed off.
12 MAN
POWER REQUIREMENT
Foreman
Laborers
Operators
13 MATERIAL
REQUIREMENT
All concrete and steel reinforcement
materials to be used shall be duly approved and installation / placing to
conform to the project
specifications, Qatar Construction Specification (QCS) and British Standards
(BS).
14 PLANT
& EQUIPMENT REQUIREMENT
a. Hand saw
b. Wire cutter
c.
Brush
d. Shovel
e. Steel brush
f.
Air
compressor
g. Plumb bob
h. Concrete pump
i.
Vibrator
j.
Trowel
k.
Spirit
level
l.
Batching
Plant
m. Transit Mixer
15 QC
APPROVAL AND OTHER DOCUMENTRY REQUIREMENTS:
All works shall be done with
accordance to Approved Method Statement and Project Specifications. Request for
inspection shall be submitted for Engineers approval prior to the works
commencement.
16 SUPPORTING
DOCUMENTATION:
This MS to be read in
conjunction with the below referenced documents
·
Contract
Specification & approved drawings.
·
Project
Quality Plan
·
Project
HSE Plan
17 DISTRIBUTION
Copies of this MS will be
circulated to the following for Information & action
·
Sr.
Construction Manager
·
Site
Engineer
·
QA/QC
Engineer
·
HSE
Engineer
18 OTHER
INFORMATION
Ensure that all the activities have been carried out
to suit the site conditions and involved
With
Site –in – charge
19 MAIN
CONTRACTORS SAFETY ENGINEERS APPROVAL
|
APPROVAL
STATUS
|
SIGNATURE
|
|
|
|
Approved
|
|
|
|
Approved
subject to compliance with the following notes
|
|
|
|
Not
Approved – with reason
|
|
20 ATTACHMENTS
(Compulsory)
·
Risk
Assessment
·
Quality
Control Inspection Checklist
·
Inspection
and Test Plan
·
PERI
– LICO ( Lightweight Column Formworks)
·
Main
Villa Elevator Shaft Frameworks
·
Main
Villa Column Construction
·
Pool
Annex Column Construction
Guard
House Column construction