Method Statement for Concreting of Columns and Shaft!

Table of Contents


1.             Scope /Objectives
2.             Reference
3.             Access/Egress
4.             Logistics
5.             Health and Safety Hazards
6.             Definitions
7.             Responsibilities / Supervision
8.             Procedures /Method to be Employed
9.             Training
10.          Working hours
11.          House keeping
12.          Manpower Requirement & Supervision
13.          Material Requirement
14.          Plant & Equipment Requirement
15.          Q.C Approvals and other Documentation
16.          Supporting documentation
17.          Distribution
18.          Other information
19.          Site Safety Engineer’s Approval
20.          Attachments (Compulsary)
·         Risk Assessment
·         Quality Control Inspection Checklist
·         Inspection and Test Plan
·         PERI – LICO ( Lightweight Column Formworks)
·         Main Villa Elevator Shaft Frameworks
·         Main Villa Column Construction
·         Pool Annex Column Construction
·         Guard House Column construction








1.       SCOPE & OBJECTIVES

The Purpose of this procedure is to ensure that Concreting works of Column and Shaft are executed in accordance with the contract requirements, hazards are analysed, safety procedures implemented all quality assurance/control activities are conducted in a systematic manner, works inspected and conformance is verified and documented for Beach Villa on BVN 55 to 60 at The Pearl Qatar.

2.       REFERENCES

Contract Drawing and specification
2.1 QCS Section 05 “Concrete Supply – Construction – Testing”
2.2 Project Health, Safety and Environmental Guidelines
2.3 Project  “inspection and Test Plan – Civil Works”
2.4 British Standard : BS 8110 – Structural use of concrete
2.5 British Standard : BS 1881 – Testing of concrete
2.6 American Standard : ACI 305 r – Hot Weather Concreting
2.7 “Method Statement for Concreting of Raft for Main Villa.”
2.8 Project Specification Section 5.

3.       ACCESS/ EGRESS

Adequate access and egress should be provided to the site. All the personnel should wear basic personnel protective equipment. All the equipment, tools and tackles being used for the work should be in good working condition and maintained. All the personnel will be provided with toolbox talk on the procedures to execute the work safely.

Access will be through designated entrance and exit pathways.

4.       LOGISTICS                                                                       

Contractor will deploy a dedicated team for the concreting works.
                                   
5.       HEALTH &  SAFETY HAZARDS
 
             Safety of the personnel and properties is to be given prime importance and all the works to be carried out without causing any accidents or property damages. Concrete works involves the following activities: shuttering and de-shuttering, fabricating and fixing reinforcements steel, transportation of concrete and placing concrete at site.

5.1    All workers involved will be trained in hazards recognition and control measures necessary especially in safe manual handling techniques and the need to keep all access clear to work area always.
5.2    Safety system / method of work covering concrete receiving, placing on site, pouring operations will be established by member management team.
5.3    Appropriate personal protective equipment (PPE) should be worn at all times.
5.4    Secure barricades within the area whenever necessary.
5.5    Washing facilities should be provided.
5.6    Formwork should be checked before concrete is put in place.
5.7    The accumulation of concrete spillage should be prevented.
5.8    The effect of weather conditions should be considered and appropriate allowances made especially on hot weather.
5.9    Only qualified and trained personnel will do the task.

6.       DEFINITIONS

AEB – Arab Engineering Bureau (Consultant/Engineer)

AMTC – Abdullah Al Muftah Trading and Contracting Co., w.l.l (Main Contractor)

MS – Method Statement

QCP – Quality Control Procedures

ITP – Inspection and Test Plan

ITA – Independent Testing Agency

7.       RESPONSIBILITIES / SUPERVISION

7.1 Project Engineer shall be responsible for the execution of this procedure and to ensure that works are undertaken in a safe manner to the requisite quality and to the time agreed timescale. He shall advise and coordinate with other contractors pertaining to access and interface requirements related to the excavation works to be undertaken.

7.2 Site Engineer shall be responsible for the site implementation of this procedure including control and the safety of the workers.

7.3 Surveyor in coordination with site engineer has the responsibility to perform all survey works according to the IFC drawings.

7.4 QA/QC Inspector shall be responsible for the supervision of tests and inspection, control approvals for testing and inspection plan and to arrange documentation required.

7.5    Safety Officer shall be responsible for the strict implementation of safety procedure during work commencements.


8.      PROCEDURE / METHOD TO BE EMPLOYED:

    8.1 General

a.          Testing and frequency of material related to concrete, design mixes, batching and mixing of concrete,          transporting of concrete, tests on green and hardened concrete and submittals shall be made in accordance            with Contract Technical Specification and the latest edition of Qatar Construction Specification (QCS).
b.          Delivery, Storage, Testing frequency of reinforcement bars and submittals shall be made in accordance with              BS 4449.

                  8.2 Reinforcement

a.         All steel reinforcement shall comply with Part 11.2 Section 5 of QCS.
b.          Reinforcement bars shall be stored over timber beams, at least 20 cm above ground level. All the bars shall               be protected from weather, dust and humidity by covering with tarpaulins or polyethylene sheets.
c.          Bar bending schedules in accordance with BS 8110 shop drawings shall be prepared by approved steel     reinforcement Fabrication Company (by ERF).
d.          Cutting, Bending and fixing of reinforcement shall be carried in compliance to BS 8666 and Part 11.4 and   11.5 Section 5 of Qatar Construction Specification (QCS) and as per the approved bar bending schedules                 and shop drawings.
e.          Lap lengths of reinforcement shall be according or indicated in the approved IFC drawing.
f.            Minimum concrete cover of 75 mm for exterior face and 40 mm for the interior face of wall shall be                 maintained as per the approved drawings and specifications.
g.          The concrete spacers blocks dimension shall be as per specified thickness cover and shall be made with the         same mix proportion as the structures.
h.          All necessary spacers and U-bars shall be provided to maintain the specified covers. U-bars bars shall be provided at 1 meter intervals on both directions to maintain the minimum concrete cover or should meet the                approved drawings & specification requirements.
i.            The fabricated bars shall be kept in position as approved in shop drawings and tied with approved tie wires.              The ends or wire shall be bent into the concrete.

    8.3 Formworks

a.          All formworks shall be done in accordance to BS 5975 and BS 8110; Section 5 of Qatar Construction           Specification (QCS).
b.          Scaffolding for working and access platform shall be erected and inspected by trained personnel.
c.          Formworks shall be design and supply by PERI Qatar (see attached – Lightweight column formwork ) and shall be in accordance with BS 5975 and BS8110; Part 9, Section 5 of Qatar construction Specification (QCS). See also attached Main Villa Elevator Shaft Framework.
d.          Formworks to be used shall be marine plywood furnish in largest practicable sizes to minimize number of   joints.
e.          Fabricate and install forms for easy removal to avoid damage to cast concrete surfaces when stripping. The         formworks shall be braced enough to withstand external forces during concrete casting.
f.            Form ties shall be factory-fabricated for securing formworks and shall be installed as per PERI Qatar            design and recommendation. Form ties designed to resist lateral pressure during concrete placing.
g.          Necessary construction joints shall be provided, with a provision of approved high strength PVC water stop     
      centrally located in the wall thickness, if applicable.
h.       Lines, levels and dimensions shall be mark by Surveyor before and after formworks installation and shall be         maintain during concrete casting.
i.          Temporary opening shall be provided for cleanouts and shall be closed and securely braced to prevent loss                of concrete mortar.
j.            Coat contact surfaces of forms with form-release agent before securing the formworks in the final position.
k.          The periods of striking / removal of formwork shall be 1 day or in compliance with Table 9.1 of QCS Section 5            Part 9.5.2

    8.4 Installation of Pipes and wall opening for MEP services

a.          All the Embedded Services / sleeves and opening for MEP works shall be in compliance with approved MEP    Drawings.
b.          Place and secure embedded items and services tied enough not to displace during concrete casting.
c.           Additional reinforcement trimmer bars shall be installed around the wall opening and pipe sleeves as per the    indicated details for trimming bars on hole in solid wall / slab in the structural drawings.
d.          All MEP services embedment shall be installed to correct sizes, line, and level to be inspected and approved             by AEB representative prior to closing of formwork.

   8.5 Transportation of concrete

a.         Transportation, delivery and handling of ready mix concrete shall be in accordance with the requirements of              BS 8500 and BS EN 206-1 and Part 8, Section 5 of Qatar Construction Specification (QCS).
b.         Concrete shall be conveyed from the mixer to its place in the works as rapidly as possible.
c.          Monitoring of time between placing of concrete shall be strictly observed and is short as   possible                 enough to prevent formation of cold joints. 

8.6    Concreting

a.       Structural concrete shall be as per approved mix design specified on structural drawings and in compliance with Part 8 Section 5 of Qatar Construction Specification (QCS).
b.       Structural concrete works shall commence upon completion / approval of reinforcement and formwork activities.
c.        Site Engineer shall ensure that the formwork provided for the required shape and dimensions are in accordance with the drawings.
d.       Reference levels for top of the concrete (see attached Main Villa Column Construction, Pool Annex Column Construction and Guard House Column Construction) shall be provided by Surveyor at the liner of forms. Steel pins / nails shall be provided at intermediate areas as guide levels for the required elevation.
e.       Adequate working platforms shall be provided for compaction / vibration and other activities.
f.         All the surfaces shall be cleaned. Foreign matters such as saw dust, wooden and wire pieces shall be removed prior to Concreting.
g.       Site Engineer shall ensure the availability of standby vibrators; pokers, hand tools, hessian clothes, polythene sheets and enough water shall be available on site.
h.       The number and size of vibrators shall be such as to ensure thorough compaction of the entire volume of concrete poured. Standby units shall also be provided.
i.         Concrete placement sequence shall be planned in a manner so that to have minimum repositioning of the transit mixer /concrete pump/crane if any.
j.         All the chutes, buckets, pokers and hand tools shall be cleaned with water before and after concreting.
k.        Surfaces of the formworks shall be kept moist and reinforcement shall be sprayed with a small amount of water prior to starting of pour.
l.         Concrete shall be ordered only after approval of the IR to place concrete by AEB representative.
m.      During hot weather conditions the following precautions / preventive measures shall be taken as applicable / required to control the effect of high ambient temperature, and low relative humidity :
·         Cooled water / ice shall be used for batching / mixing concrete. Water shall be cooled by using chillers, ice (if necessary) to maintain concrete temperature equal to or below 32 deg. C.
·         Maximum shade temperature during placing of concrete shall be not more than 35 deg. C.
·         To keep cool, transit mixer drum surface shall be painted white, which shall minimize solar heat gain.
·         Transit mixers drum surfaces shall be kept cool by covering them with wet Hessian clothes, damp by spraying water. Water shall be sprayed to the concrete mixer drum before batching and during delivery.
·         Pouring shall be planned / scheduled on the evening hours when the weather condition is favourable and adverse exposure of the concrete to the environment can be avoided.
·         Time to transport, place, consolidate and finish the concrete shall be minimized by proper planning and coordination.
n.       Concrete shall be delivered to site and used within 90 minutes after the introduction of water and shall be placed and compacted to its final position.
o.       The delivery ends of the pump hose shall be kept as close as possible to the delivery points; the drop height shall be minimized to 1.5m (max) to avoid segregation.
p.       To maintain the drop height, a flexible hose shall be connected to the outlet of the pump then it will insert inside the wall forms or by specially designed drop holes around 200x200 mm shall be provided in the shuttering at every 2 meter C/C and at every 1.5 meter height of shuttering to keep the minimum drop height.
q.       Vibrators shall be operated at regular intervals to produce dense, compact, homogeneous concrete surface without segregation and ensure thorough compaction of the entire volume of the concrete.
r.         Vibrators shall be withdrawn slowly to prevent the formation of voids and shall not be placed against compacted concrete. It shall not be used for transporting concrete inside forms.
s.        The concrete will be vibrated as work proceeds. Once the concrete has reached the required height, the exposed surface will be trowel and covered for protection.

8.6          Curing of Concrete

a.       Water to be used for curing shall be free from salt, harmful matters and other impurities.
b.       Concrete shall be cured to a minimum of seven days.

8.7          Dimension Tolerance for Concreting works (As per QCS Part 9.7; Section 5)

a.       All laying-out dimensions                                                                                                      ± 5mm
b.       Section of concrete members                                                                                               ± 5mm
c.        Surface of foundations against ground                                                                              ± 10mm
d.       Top surfaces of foundations, bases and piers                                                                  ± 20mm
e.       Surface level of floor slabs (5-meter straightedge)                                                          ± 5mm
f.         Surface level of slab to datum                                                                                              ± 10mm
g.       Plumb of columns and wall in storey height                                                                              ± 5mm
h.       Plumb of column and wall in full building height                                                  ± 20mm
i.         Inside faces of elevator shafts in storey height                                                                 ± 5mm
j.         Inside faces of elevator shafts in full building height                                                       ± 10mm

8.8 Testing:

a.       Testing on concrete aggregates is to be as per QCS Section 05 part 6.4.
b.       Slump and temperature of fresh concrete supplied to site shall be monitored and checked in accordance with QCS   Section 05.
c.        Strength testing (cubes): 3 cubes for every 25 cum minimum or 1 set per day that concrete is placed, one tested at 7 days and two tested at 28 days.
d.       Testing of steel reinforcement will be done every delivery to have random checking in conformity with QCS section 5 part 11.
 


8.9 Protection of Sub Structures:

         All structures below ground to be protected with an approved water proofing system.

8.10 Embedment’s:

a.       Anchor bolts to be fixed to correct level and line with templates and secured firmly to prevent any displacements during concreting.
b.       Corner Angles to be embedded in concrete shall be placed in position and suitably fixed to form and or tied to rebars.
c.        PVC Ducts and Sleeves are placed in position, and supported adequately prior to concreting, by securing to formwork and or rebars.
d.       No welding shall be done to the rebars, for fixing the embedments.
                                                                                             
         9    TRAINING
      
Relevant trainings and orientations have been provided to person who will perform their specified task.

10     WORKING HOURS

As per approved site schedule.

11     HOUSE KEEPING
                                                                                               
Working Areas will be kept clean by disposing the waste materials at the designated areas.  At the end of  days’ work, installation supervisor will ensure that the debris are disposed off.


12     MAN POWER REQUIREMENT

Foreman
Laborers
Operators

13     MATERIAL REQUIREMENT

        All concrete and steel reinforcement materials to be used shall be duly approved and installation / placing to conform to     the project specifications, Qatar Construction Specification (QCS) and British Standards (BS).

14     PLANT & EQUIPMENT REQUIREMENT
                                                                                               
a.       Hand saw
b.       Wire cutter
c.        Brush
d.       Shovel
e.       Steel brush
f.         Air compressor
g.       Plumb bob
h.       Concrete pump
i.         Vibrator
j.         Trowel
k.        Spirit level
l.         Batching Plant
m.      Transit Mixer

15     QC APPROVAL AND OTHER DOCUMENTRY REQUIREMENTS:

All works shall be done with accordance to Approved Method Statement and Project Specifications. Request for inspection shall be submitted for Engineers approval prior to the works commencement.
            
16     SUPPORTING DOCUMENTATION:

This MS to be read in conjunction with the below referenced documents

·         Contract Specification & approved drawings.
·         Project Quality Plan
·         Project HSE Plan

17     DISTRIBUTION

Copies of this MS will be circulated to the following for Information & action
·         Sr. Construction Manager
·         Site Engineer
·         QA/QC Engineer
·         HSE Engineer

18     OTHER INFORMATION

               Ensure that all the activities have been carried out to suit the site conditions and involved
                                                                          With Site –in – charge


19     MAIN CONTRACTORS SAFETY ENGINEERS APPROVAL

APPROVAL STATUS
SIGNATURE

Approved


Approved subject to compliance with the following notes

Not Approved – with reason










20     ATTACHMENTS (Compulsory)

·         Risk Assessment
·         Quality Control Inspection Checklist
·         Inspection and Test Plan
·         PERI – LICO ( Lightweight Column Formworks)
·         Main Villa Elevator Shaft Frameworks
·         Main Villa Column Construction
·         Pool Annex Column Construction
Guard House Column construction

2 comments:

  1. I would like to thank you for the efforts you have made in writing this article. I am hoping the same best work from you in the future as well.
    click here

    ReplyDelete
  2. I like the helpful info you provide in your articles.
    I will bookmark your blog and check again here frequently.
    I am quite sure I will learn many new stuff right here!
    Best of luck for the next!We at Propertyhunters. this is our service web site. please visit our web site.
    Thank you.Apartments for sale in Doha Qatar

    ReplyDelete